St James’ Interchange A737 link closure rescheduled for November
The postponed closure will run from Friday, November 6 to Tuesday, November 10, with traffic diverted via the M8 eastbound on-slip.

At St James’ Interchange, the postponed closure of the A737 St James’ Viaduct link is now scheduled to run from Friday, November 6 until Tuesday, November 10. The works had been planned for the weekend beginning October 23 but were postponed because of Storm Boelo.
Amey confirmed the revised dates on behalf of Transport Scotland. The closure will affect traffic using the viaduct link, with drivers directed onto a signed diversion to rejoin the M8. The year and daily start and finish times for the closure have not been announced.
How the diversion will work
Traffic will be directed onto the A737 off-slip to St James’ Interchange. From there, drivers can join the M8 using the Junction 29 eastbound on-slip; the diversion ends at that point.
The announced route takes traffic away from the closed link and back onto the motorway in the eastbound direction. The update does not specify which lanes or other approaches will be affected, or give details of any alternative routes for drivers who cannot use the diversion.
What happens after the works
Amey says the bridging plates and the 30mph speed restriction will be removed after the weekend closure is completed. The update does not give a separate time for their removal or explain how the work will be carried out.
Drivers should note that the stated closure period runs through Tuesday, November 10, rather than ending on Sunday. No further details about the works, their duration each day or possible changes to the timetable have been announced.
This report draws on information from Glasgow Times.
Editorial checks passed Facts, figures and quotes checked against 1 source
Add Glasgow News as a preferred source on Google